Notes:
4/2/2025 9:44:49 AM
& replace (79) services due to reliability. Permit to include all necessary restoration.
4/4/2025 8:35:29 AM
1. 692’ based on new calculation. Construction drawing says replacing 78 services but there are many branch services that are being replaced. I came up with 48 services connecting to the main 15 long side and 33 short side.
2. Drill head will be ¾” to install ½” plastic.
3. Restoration - 1’ T-cut at current asphalt depth is what we will be restoring per Vallejo’s requirements.
4/4/2025 8:53:22 AM
35511006
Severus – Mini to River Pines PCI 92 (Will require Slurry Seal)
Severus – River Pines to Jack London PCI 92 (Will require Slurry Seal)
Springfield – Mini to Severus PCI 24
River pines – Severus to Severus PCI 19
4/4/2025 9:53:38 AM
Per PG&E they are good with restoration requirements.
4/25/2025 1:47:19 PM
Per Traffic:
Conditions of approval.
Notify SolTrans and homeowners of construction dates and times. Install 'No Parking' signs 72 hours prior to start of each phase to restrict parking within work zone, at flagging zone and 50 feet prior to flagging zone (for traffic being diverted from normal travel lanes).