Notes:
3/14/2025 8:16:58 AM
replace ~5613' of gas main and (73) gas services due to reliability. Permit to include pre & post construction CCTV cross bore sewer inspections & all necessary restoration.
3/14/2025 10:16:17 AM
35515265 – PTAP Report 22
Severus – Meadows to Catalina PCI 18
Catalina Ct – PCI 22
Pelican Dr – Severus to Vergel PCI 20
Vergel Terr – Meadow to Auburn PCI 23
Newport Dr – Auburn to Severus to PCI 35
Auburn Dr – Severus to Sandpiper PCI 25
Old River Ct – Auburn to Cul de Sac PCI 32
3/24/2025 7:58:00 AM
Pending Confirmation rather the permit will be applied for as all open cut or revised for directional boring.
3/25/2025 3:17:37 PM
After talking to the job owner restoration will be 1’ T-cut at current asphalt depth is what we will be restoring per any permit requirements.
4/28/2025 3:17:52 PM
Restoration confirmed Typical 1’ T-cut at current asphalt depth is what we will be restoring per Vallejo’s requirements.
4/28/2025 3:18:36 PM
This job went through a revision and added some main and services north of Catalina Ct and Severus Dr up to Yankee Jim Ct. Can you confirm if the TCP covers this additional scope and if we can get the permit application updated as well. Scope will be to open trench main and bore services. Went from 4600LF of main to 4880LF and an additional 7 services.
4/29/2025 7:56:28 AM
4880 LF open Trench, 1115 LF boring with 3/4" diameter drill head
4/30/2025 10:01:37 AM
Per Traffic: Approved with Conditions
TCP Sheets 34-36 (Phase 13) – Proposed work zone conflicts with existing bus stop (Stop ID: 825008). Contact Soltrans for bus stop coordination.